Houghton 2019 Reports

Houghton Section Trail Work Reports – 2019

[ Back to Houghton Section Page ]

Date
Name
Trail
Hours
Work
Volunteers
Remaining Work
Comments
2019-01-19Bob FlaggHeadquarters Path0.75Performed minor brushing removing branches from trail for section that crosses road. Picked up small bag of trash.
2019-01-19Bob FlaggQuincy Path (FBH)1Performed minor brushing removing branches from trail. Removed debris blocking flow at small bridge. Picked up half small bag of trash.Need to remove rocks under small bridge to improve flow.
2019-01-26Bob FlaggHoosicwhissick Path (FBH)1.5Walked path along Houghtons Pond picking up small pieces of trash like butts, bottle caps and straws where the debris washes ashore. Removed branches from trail.Pond was frozen so good shore cleanup should be done when the water thaws.
2019-01-26Bob FlaggPrescott Foot Path0.75Walked path along Houghtons Pond from intersection with Hoosicwhissick Path to end of trail near concession stand.Picked up small pieces of trash like butts, bottle caps and straws where the debris washes ashore. Removed branches from trail.Pond was frozen so good shore cleanup should be done when the water thaws.
2019-01-26Bob FlaggHeadquarters Path1Removed branches from trail from parking lot near State Police office to intersection with White Pine Path. Cleared large section of green briar from both sides of trail. Picked up small bag of trash.
2019-01-26Bob FlaggWhite Pine Path (FBH)0.25Removed branches from trail.
2019-02-02Bob VogelBarre Trail0.5Picked up fallen branches, street to 2130.
2019-02-02Bob VogelBoyce Hill Trail1.5Cut up good sized double tree down across the trail. Required cutting both trunks twice, and levering both pieces to the side of the trail.The whole rest of the trail, I just hiked in via Barre to cut up this tree, which had been blocking the White Triangle Trail since the fall.
2019-03-29John HahnfeldBoyce Hill Trail1Removed fallen limbs, branches from the trail.A short way onto the trail, perhaps a hundred yards from the 2153 marker, there's a fallen tree suspended over the trail. The trial is passable, but ideally this should be removed. ALSO, at the bottom of the Boyce Hill Trail, turning right on to the Doe Hollow Path, at about 110 yards there's a tree fallen right across the trail that needs to be stepped over. Not a problem, probably, for hikers or horses, but an impediment to any wheeled traffic.
2019-03-29John HahnfeldBurnt Hill Path1Cleaned branches and limbs from the path.Will return soon to clean out grade reversals.About 400 feet in from the 2111 marker the top of a fallen tree was blocking the trail. I was able to deal with the smaller diameter branches, but there's still some stuff that's too thick for my saw, and which should be trimmed a little further back from the trail with a chain saw. Probably 15 minutes work for a chain saw.
2019-04-05John HahnfeldBurnt Hill Path1.5Raked out all grade reversals on trail.
2019-04-12Judy JacobsBugbee Path36Raked side ditches and culverts from 2111 to in between 2155 and 2172.Bryan Rooney, Irene Hunt, Caroline Mazzola, Chris Read, Scott McCaughy, Barbara Sutherby, Chris Detwiller, Joseph Simonelli, Sherry Cutis, Kim Martin, Jame MacDonald, Monique Screen-BerryThere is a side ditch that hasn't been done in years that is just around 2075, off of Bugbee Path. There are also culverts that need cleaning along Bugbee Path from 2017 to 2111.
2019-04-25Judy JacobsBugbee Path45Cleared out side ditches that have been grown over; dug out culverts, cut brush.Ondera Flowers, Ted Lensdale, Kimberly Saracino, Sarah Marks, Isaque Medeiros, Christopher Pontbriand, Dean Cascadden, Matt Kieras, Christopher Morris, Matthew Kalin, Jade Rivera, Kelly Kyson, Dan Boermeester, Chris WardThere's a culvert just before 2053 that they uncovered, but it is still somewhat blocked on the north side of the trail. Water is pooling on the trail because it can't flow through the culvert.
2019-04-27Bob FlaggMassachuseuck Trail35Cleaned and improved all grade reverals from Forest Path to Marker 2152. Removed rocks, leaves, sticks and other debris from ditch and outflow.Shubha Chungi, Robert Priest, Joe Nelson, Kristen Kercher, Nathan Mahan, Cristhi Anne, Ian McLachlan, Emilie Bent, Bob Kittredge
2019-05-11AMCSEM-Pete TierneySkyline Trail21Cleaned stairs on both sides of Buck Hill, replaced missing stair on west side of Buck Hill, cleaned out three grade reversals, removed rocks and scree from trail, cut back vegetation.Natalie, Bill, Lars, Randy, Sue, Tim
2019-05-31John GoldrosenForest Path2.5Cleaned out blocked culvert under trail at 2194. Cleared downed branches and twigs from trail, and cut back overhanging vegetation. Cut up and removed downed trees that were alongside trail.Mountain bikers rode around the sides of wet and muddy areas during the winter and spring, leaving ruts and widening the trail. Can we work with the mountain-biking association to educate riders that it is better to ride through the puddles (or not ride at all on muddy trails), than to ride around them?
2019-06-07Chris MullinAMC Footpath1BrushingScrub brush at the top
2019-06-07Chris MullinFern Spring Foot Path0.25brushing
2019-08-03Dexter RobinsonHeadquarters Path38.5Brushed trail from Houghton's Pond parking lot (Hillside St.) to 2175.Barry Young, Joanne Velez, Anthony Camache, Anna Lee, Michael Shepherd, John Harrell, Sarah Scrugg, Kelly McCree, Alysen McDonough, Grace GrielinkRemainder of Headquarters Path to Rt. 28Several areas flood in the Spring. May need to consider re-routing.
2019-08-19John HahnfeldBoyce Hill Trail0.75Remove a few small trees that were beginning to look like possible nuisances for equestrian users of the trail.
2019-08-19John HahnfeldBurnt Hill Path0.75Removed part of a large pine that had fallen, landing with the uppermost part of the tree protruding a few feet onto the trail. I was able to remove the most rotted part and pitch it off the trail, but there remains enough for a couple passes with a chain saw that should also be removed to clear it from the trial entirely.About 100 yards uphill from 2092, on the Burnt Hill Path, three or four feet of a large fallen pine are still protruding onto the trail. A couple passes with a chain saw will make quick work of this, and it should then be removed from the trail, in addition to what I've already removed.
2019-08-18Bob FlaggDoe Hollow Path0.75Cleaned large swale and ditch at 2153 and removed large branch about 100 yards up the trail.
2019-09-27John HahnfeldBoyce Hill Trail0.5Removed minor debris from trail.There are TWO locations where substantial dead trees have fallen across the trail. 1) Just south and downhill from #2151, and 2) near #2130. Both of these require a chain saw to remove.
2019-09-27John HahnfeldBurnt Hill Path0.5Removed minor debris from trail.None at this time.
2019-09-28AMCSEM-Pete TierneySkyline Trail16Hillside Street to eastern slope of Tucker Hill, Route 28 to western slope of Buck Hill.Bill, Sue, Skip, Rob, PaulContinue working on portion of trail not covered today.
2019-10-12Bob FlaggBouncing Brook Path1.25Walked trail performing minor brushing, cleaned nick near pipeline end of trail.
2019-10-19John HahnfeldBoyce Hill Trail1Picked up debris from the trail after the storm of 10/16 and 10/17.Still (very) minor debris that I'll get another time.At the intersection of Boyce Hill Trail with the Skyline trail, about 50 ft. up the Skyline, there is a tree down across the Skyline Trail. It is not preventing use of the trail, but is lying directly across it.
2019-10-19John HahnfeldBurnt Hill Path1Picked up debris from the trail resulting from the storm of 10/16 and 10/17. Only minor debris remains. there is a tree down across the Boyce Hill Trail approximately 150 ft. from the intersection with the red dot trail. It allows foot traffic, but would prevent bike traffic and may impede equestrian traffic.
2019-10-25AMC-SEM Skip MayslesSkyline Trail22This trail work outing had 2 parts; 1st to complete work started on Sept 28, 2019 and to remove parts of a blow down approx. 75 feet east of junction 2117.AMC-SEM had a trail work event on Sept 28 and had two crews (total of 6 volunteers) working from each end. We cleaned stairs, cleared water bars, removed loose rocks and trimmed back vegetation. We ran out of time and we did not finish our work. On Oct 25, Pete and I returned to complete the previous work and to remove a recently reported blow down from a storm which had blocked the trail approx. 50 yards east of junction 2117. We finished the work from Sept 28 trail work event.
Also located and removed the large branches of the fallen tree which had blocked the trail, but were not able to remove the trunk. The Skyline trail is now passable in this area.
Pete Tierney, FoBH/AMC-SEMThe section of the Skyline Trail, 50 yards east of junction 2117, had previous blow downs which were reported a few years ago. Now we can add another blow down in that same cluster. These will need a chain saw to remove.
2019-11-07John HahnfeldBoyce Hill Trail1Picked up debris from recent storm. Nothing major on this trail.About 100 yards downhill from #2151 there's a tree that fell away from the trail, but there's about three feet that should be taken off of the stump end to keep it entirely off the trail.
2019-11-07John HahnfeldBurnt Hill Path1Picked up debris from recent storm.11At intersection #2111, there's a large oak down across the trail. Defnitely a hazard that would prevent bike or equestrian use of the trail, and may present a danger to hikers. Should be removed ASAP.
2019-11-07John HahnfeldBurnt Hill Path1Picked up debris from recent storm.11At intersection #2111, there's a large oak down across the trail. Defnitely a hazard that would prevent bike or equestrian use of the trail, and may present a danger to hikers. Should be removed ASAP.
2019-11-11John GoldrosenForest Path4Cleaned culverts and drainage paths. Removed downed branches from trails. Cut off limbs from three downed trees, leaving trunks that were too large for work with a handsaw.Two large tree trunks remain across the trail, between the Bugbee Path and the Pipeline (2190 and 2189). I cut off what I could with a handsaw, so that people can climb over them. There is also a trunk encroaching on the trail (but not blocking it), north of the intersection with the Skyline Trail.
2019-11-16Bob FlaggOblique Path0.75Performed minor brushing, removing branches from trail. Cleaned side ditch and removed rocks in front of culvert.
2019-11-16Bob FlaggBeech Hollow Path0.75Performed minor brushing on trail, removing downed branches.
2019-11-16Bob FlaggBolton Foot Path0.5Walked trail removing branches from trail.
2019-11-16Bob FlaggBurnt Hill Path1Cleaned out grade reversal closest to 2092, removed leaves from remaining ones heading up the hill.
2019-11-16Bob FlaggDoe Hollow Path0.75Performed minor brushing from 2129 to 2132.
2019-11-16Bob FlaggPig Rock Path0.75Performed minor brushing and removal of branches from trail.
2019-11-17Bob FlaggDover Trail1.5Removed two very large branches blocking trail, fot three hikers passing by to help sawing thru a 10 inch log.
2019-12-01Bob FlaggBuck Hill Path1Walked path removing branches and cleaning grade reversals.
2019-12-08Bob FlaggAthol Path1Walked trail removing branches from trail including very large branch hanging over trail.